This roadmap uses relative phase identifiers (P0 through P9) rather than calendar dates. Duration estimates are relative units for planning purposes only.
Phase Overview
Gantt-Style Timeline
Phase Dependencies
Critical Path
The critical path runs: P0 → P1 → P2 → P3 → P5 → P6 → P7 → P8. P4 (Evaluation + Benchmarking) runs in parallel with P3 and feeds into P5. P9 is an optional extension that depends on P8.Phase Entry and Exit Criteria
Each phase has explicit entry criteria (what must be true to start) and exit criteria (what must be true to finish). See individual phase pages for complete criteria:- Phase 0: Consistency-audited specification
- Phase 1: Working compatibility pipeline
- Phase 2: Validated basic merge
- Phase 3: Multiple merge strategies operational
- Phase 4: Benchmark engine with integrity controls
- Phase 5: Evolutionary loop producing candidates
- Phase 6: Quantized deployable models
- Phase 7: Air-gapped deployment capability
- Phase 8: Enterprise pilot validated
- Phase 9: Optional RAG architecture specified